Review IA Reports & Request Changes

After Implementing Agencies submit report, the State Agency can review IA reports and request changes. Each IA report is reviewed separately.
NOTE: All data listed on this page is example data only and does not represent actual data within N-PEARS.
  1. From the homepage, click Work on the Annual Report.
    Work on the 2023 Annual Report button
     
  2. From the Annual Report Overview page, go to the navigation menu and select Review Implementing Agency Reports.
    review implementing agencies reports
  3. The Review Implementing Agency Reports section lists each IA within the state. Click the arrow to view a list of modules for a specific IA report.
    Review Implementing Agencies Arrow button
  4. Click the Review button to examine data from a specific module.
    Review button
  5. Review data is listed in different formats for each module:
    a. Executive Summary: All details are listed on the review page.
    Review executive summary
    b. Project and Activity Results: To view details for each project, click the corresponding arrow. Click the Reviewed checkbox for each project.
    review projects arrow
    c. Evaluation Reports: To view details for each evaluation, click the corresponding arrow. Click the Reviewed checkbox for each evaluation.
    evaluation review arrow button
    d. Success Stories: To view details for each Success Story, click the corresponding arrow. Click the Reviewed checkbox for each story.
    Review Success Stories
    e. Challenges and Modifications: All details are listed on the review page.
    Review Challenges and Modifications
    f. Coordination & Collaboration: All details are listed on the review page.
    coordination and collaboration review section
    g. SNAP-Ed Financial Reporting: Initially, the Total Agency Expenditures is listed. Click each tab to view budget details for Program Income and Direct Cost Breakdown:
    Review SNAP-Ed Financial Reporting
     
  6. Once all details within a module have been reviewed, click Mark as Reviewed.
    Mark as Reviewed Button
  7. The Review IA Reports section appears, and the module is marked as reviewed.
    Module marked as reviewed
  8. If the review of IA Reports reveals changes are needed within an IA report, click Request Changes.
    Request Changes Button
  9. A comment field appears. List changes needed or questions to answer. Then click Request Changes.
    Request Changes Button
  10. Comments are emailed to all IA staff with access to the SNAP-Ed National PEARS system. The status of the IA report is listed as Changes Requested.
    Changes Requested
  11. Once all modules within an IA report have been reviewed and no additional changes are needed, click Approve.
    Approve Button
  12. The Approve Report window appears. Read the approval details and click Approve.
    Approve Report Button
    The IA Report’s status is listed as Approved.
    Implementing Agency plan approved icon.
  13. Repeat steps 3-12 for each IA in the state. Review report modules, request changes (as needed), and approve the report.